Scope
The project will create a safe, secure and operationally ready environment for the incoming main contractor. The enabling works are complex and multifaceted, particularly given the live nature of the data facility. Key elements include:
- Completion of a pre-commencement asbestos Refurbishment and Demolition (R&D) survey
- Safe removal and disposal of all identified asbestos-containing materials
- Full structural demolition of existing buildings and infrastructure
- Identification, isolation and removal of redundant services
- Installation of new service routes to support forthcoming construction phases
- Coordination of all activities in line with client and regulatory safety standards
Challenges and Expertise
The site’s location within a historically bombed area of London introduced potential UXO risks and proximity to an existing dock wall. Downwell’s pre-construction team undertook detailed archival research and ground probing to assess these hazards. Additional banksmen and strict excavation controls ensured all works were executed safely, methodically and without incident.
Outcome
The works have been delivered safely and efficiently, providing the client with a cleared and compliant site ready for the next stage of development.